On the roof of the older hall SO 01, we installed ballast structures, DC trays, and cabling. About two-thirds of the roof is already covered with photovoltaic panels.
On the new hall SO 02, the ballast structures and DC trays are fully installed. DC cabling is being laid, followed by the installation of photovoltaic modules.
The entire project is designed to integrate both parts of the hall into a single PV system with optimized output and efficient roof space utilization
The installation is carried out with minimal disruption to the operation of the facility and with preparation for smooth connection to the distribution network.